Planning · 3 min read

Bathroom Renovation Timeline: A Week-by-Week Plan

By the House of Ceramic team, Surat ·

Illustration: one bathroom in four stages, stripped brick and pipes, blue waterproofing under a flood test, tiles with spacers, and the finished basin

The short answer

A small bathroom follows a fixed order: choose and check everything, strip out, plumbing and frames, floor slope and waterproofing, flood test, tiles, grout, then sanitaryware. This plan spreads it over four working weeks. Your fixer sets the real dates.

  • 01The order matters more than speed. Waterproof and flood test before any tile goes down.
  • 02Data sheets fix the waits: about 24 hours for a flood test and 24 to 36 hours before grouting a floor.
  • 03Have every tile, drain, frame and fitting on site and checked before strip-out.
  1. Before week 1

    Choose, order and check

    Pick tiles, pan, taps, drain and frame. Open the boxes and check batch numbers and sizes against the drawing.

  2. Week 1

    Strip out, plumbing, frames

    Remove old tile and fittings. Move pipes and fix any concealed cistern or wall-hung frame now, before the wall hides them.

  3. Week 2, first half

    Slope and waterproofing

    Lay the floor so water runs to the drain, then apply the waterproof layer up the walls. Wet mortar beds cure about 72 hours first (Hydro Ban sheet).

  4. Week 2, second half

    Flood test and wait

    Flood the floor and watch the level. Sheets give 24 hours (Hydro Ban) or 48 hours (SikaTile-110). No tile until it passes.

  5. Week 3

    Walls first, then floor

    Press each tile into full adhesive. Keep off the floor until it sets: MYK Laticrete 325 lists 16 to 24 hours.

  6. Week 4, first half

    Grout and seal

    Grout walls after 4 to 6 hours and floors after 24 to 36 hours (SikaCeram-155). Seal corners with flexible sealant, not grout.

  7. Week 4, second half

    Fit, test, clean

    Fix pan, basin, mixers and shower. Run every tap and look for drips. Heavy loads wait 28 days (MYK Laticrete 325).

Nobody can promise one number of days for every house. The waits below come from data sheets; the week split is ours.

Why does waterproofing go before tiling?

Tile and grout are not waterproof on their own. The layer under them stops water reaching the slab. A leak found after tiling means breaking the floor, so the flood test comes first.

Water should meet the waterproof layer before it meets the slab.
Floor tiles being set onto fresh adhesiveA hand finishing a tile joint on a pale floor

Tiles first, joints after a day. Rushing the gap is what cracks later. Photo: MYK Laticrete.

What most often delays a bathroom?

  • A tile or fitting arrives late, or from another batch.
  • The flood test fails, the layer is repaired and tested again. Keep spare days.
  • A frame or drain is set at the wrong height. Cheap to fix behind the wall, costly after the tile.

Bring your drawing to the showroom before strip-out and we will check it against your sanitaryware, drain and adhesive.

Questions people ask

How long does a bathroom renovation take?

It depends on size, the base and how fast materials arrive. This post plans a small bathroom over four working weeks, including the waits data sheets fix. Your fixer sets the real dates.

What order should a bathroom renovation follow?

Strip out, plumbing and frames, floor slope, waterproofing, flood test, wall tiles, floor tiles, grout, then sanitaryware and taps. Skipping the flood test is the costly mistake.

How long should I wait before grouting?

SikaCeram-155 lists 4 to 6 hours for walls and 24 to 36 hours for floors. MYK Laticrete says at least 24 hours for 325 High Flex at 21 degrees C. Use the sheet for your adhesive.

Sources

  1. LATICRETE Hydro Ban data sheet (flood test about 24 hours; wet mortar beds cure 72 hours first; longer when cool or humid)
  2. Sika: SikaTile-110 SecureProof data sheet (flood test at 48 hours)
  3. Sika India: SikaCeram-155 Wet Room data sheet (grouting walls 4 to 6 hours, floors 24 to 36 hours)
  4. MYK Laticrete: 325 High Flex data sheet (foot traffic 16 to 24 hours; grout after at least 24 hours at 21 degrees C; heavy traffic 28 days)